Click here for an interactive map of the Emmett Township Local Road Project
2022 construction overview:
Read the press release
PROJECT UPDATE JUNE, 30 2022:
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- President Streets
- Bach/Hoover Subdivision
- E Drive N, Dead End – Juanita
- 6 Mile Rd
- 6.5 Mile Rd
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- Vale St
PROJECT UPDATE JUNE, 23 2022:
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
The following streets have been paved with a base layer of HMA:
- President Streets
- Bach/Hoover Subdivision
- E Drive N, Dead End – Juanita
- 6 Mile Rd
- 5 Mile Rd
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- Vale St
6 Mile and 6.5 Mile are scheduled to be paved with a base layer today (6 mile), and tomorrow (6.5 Mile).
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
The following streets have been paved with a base layer of HMA:
- President Streets
- Bach/Hoover Subdivision
- E Drive N, Dead End - Juanita
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Vale St
- 6.5 Mile Rd
- 6 Mile Rd
*Roads that are currently pulverized will be watered regularly for dust control
PROJECT UPDATE JUNE 9, 2022:
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- President Streets
- Bach/Hoover Subdivision
- E Drive N (6.5 Mile to Dead End)
- Vale St
- 6.5 Mile road
- 6 Mile Rd
PROJECT UPDATE JUNE 2, 2022:
Paving is currently scheduled for Christian Drive this morning around 10:00 a.m.
The following streets have been paved with a base layer of HMA:
- Lamson
- Bach
- Embury
- Hoover
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
The following streets are currently pulverized/milled:
- E Drive N (6.5 Mile to Dead End)
- Vale St
- 6.5 Mile road
- 6 Mile Rd
- Christian Dr
*Roads that are currently pulverized will be watered regularly for dust control
PROJECT UPDATE MAY 26, 2022:
The following streets have been paved with a base layer of HMA:
- Lamson. The rest of the neighborhood, (Bach, Embury, Hoover) is not paved yet, we didn’t pave Tuesday due to scheduling conflict. Tried Wednesday but were rained out. Should be back there next week
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Vale St
- 6.5 Mile road
- 6 Mile Rd
- Christian Dr
*Roads that are currently pulverized will be watered regularly for dust control
PROJECT UPDATE MAY 23, 2022:The President Streets Subdivision, (Eisenhower, Nixon, Eastland, Dulles, Humphrey and Knowland) have had the base layer of HMA paved.
The following streets are scheduled to be paved with a base layer of HMA on Tuesday, 5/24/22:
- Hoover, Bach, Embury, Lamson
- E Drive N, Beadle Lake Rd – Dead End
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Vale St
- 6.5 Mile road
- 6 Mile Rd
*Roads that are currently pulverized will be watered regularly for dust control
PROJECT UPDATE MAY 13, 2022:The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Eisenhower (Milled)
- President Streets Subdivision
- Vale St
- 6.5 Mile road
*Roads that are currently pulverized will be watered regularly for dust control
PROJECT UPDATE MAY 5, 2022:The following streets have been paved with a base layer of HMA:
- Powell
- Hammond, N of Westbrook
- Westbrook
The Following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Eisenhower (Milled)
- President Streets Subdivision
- Vale St
- 6.5 Mile road
Trenching has begun on 6 mile rd with pulverization to follow, likely next week.
Christian and Ryan’s Run will be milled today ,5/5, after being rescheduled from this past Tuesday.
PROJECT UPDATE APRIL 28, 2022:The following streets have been paved with a base layer of HMA:
- Juanita, from E Drive N to End
- Tower Rd
- Westbrook
- Powell
- Hammond, N of Westbrook
The Following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, from 6.5 Mile – End
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Eisenhower (Milled)
- President Streets Subdivision
- Vale St
- 6.5 Mile road
The following streets are scheduled to be pulverized/milled Tuesday, 5/3/22:
- Christian Drive/Ryan’s Run (Mill 1.5”)
Punch List Items rolled over from last year will be addressed in the coming weeks based on priority.
PROJECT UPDATE APRIL 21, 2022:The following streets have been paved with a base layer of HMA:
- Juanita
- Orbit
- Westbrook
- Powell
- Hammond, N of Westbrook
The following streets have been pulverized and will have driveways removed while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Tower Rd
- Eisenhower (Milled)
- President Streets Subdivision
- Vale St
The following streets are scheduled to be pulverized this Thurs/Fri:
- Bach/Hoover/Embury
- 6.5 Mile Rd
The following streets were striped with pavement markings on Wednesday:
- E Drive N (Beadle Lake Rd to 9 Mile Rd) – 1st Application
- D Drive N (9 Mile Rd to M-311) – 1st Application
- L Drive N (Gravel to 12 Mile Rd) – 2nd Application
- D Drive N (6.5 Mile Rd to Beadle Lake Rd) – 2nd Application
- G Drive N (Raymond Rd to Wattles Rd) – 2nd Application
- E River Rd (Raymond Rd to G Drive N) – 2nd Application
- 8.5 Mile Rd (B Drive N to D Drive N) – 2nd Application
- Grenville (Columbia Ave to City Limits) – 2nd Application
Punch List Items rolled over from last year will be addressed in the coming weeks based on priority.
PROJECT UPDATE APRIL 14, 2022:The following streets have been pulverized and will have driveways removed while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Orbit
- Juanita
- Westbrook
- Tower Rd
- Eisenhower (Milled)
The following streets are scheduled to be pulverized this Thurs/Fri:
- President Streets Subdivision
- Vale St
The following streets are next in line for driveway cutting and berm grading:
- Hoover
- Bach
- Embury
The following streets are scheduled to be striped with pavement markings next week:
- E Drive N (Beadle Lake Rd to 9 Mile Rd) – 1st Application
- D Drive N (9 Mile Rd to M-311) – 1st Application
- L Drive N (Gravel to 12 Mile Rd) – 2nd Application
- D Drive N (6.5 Mile Rd to Beadle Lake Rd) – 2nd Application
- G Drive N (Raymond Rd to Wattles Rd) – 2nd Application
- E River Rd (Raymond Rd to G Drive N) – 2nd Application
- 8.5 Mile Rd (B Drive N to D Drive N) – 2nd Application
- Grenville (Columbia Ave to City Limits) – 2nd Application
Punch List Items rolled over from last year will be addressed in the coming weeks based on priority.
PROJECT UPDATE APRIL 7, 2022:The following streets have been pulverized and will have driveways removed while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Orbit
- Juanita
- Westbrook
The following streets are scheduled to be pulverized next Thurs/Fri:
- President Streets Subdivision
- Tower Rd
- Vale St
The following streets are next in line for driveway cutting and berm grading:
- Hoover
- Bach
- Embury
The following streets are scheduled to be striped with pavement markings on April 14th:
- E Drive N (Beadle Lake Rd to 9 Mile Rd) – 1st Application
- D Drive N (9 Mile Rd to M-311) – 1st Application
- L Drive N (Gravel to 12 Mile Rd) – 2nd Application
- D Drive N (6.5 Mile Rd to Beadle Lake Rd) – 2nd Application
- G Drive N (Raymond Rd to Wattles Rd) – 2nd Application
- E River Rd (Raymond Rd to G Drive N) – 2nd Application
- 8.5 Mile Rd (B Drive N to D Drive N) – 2nd Application
- Grenville (Columbia Ave to City Limits) – 2nd Application
Punch List Items rolled over from last year will be addressed in the coming weeks based on priority.
PROJECT UPDATE APRIL 5, 2022:The following streets have had driveways cut and berm graded and are currently being pulverized this week, April 5 (Mon-Wed):
- E Drive N (6.5 Mile to Dead End)
- Orbit
- Juanita
- Westbrook
- President Streets Subdivision
The following streets are next in line for driveway cutting and berm grading:
- Hoover
- Bach
- Embury
On April 14, the following streets are scheduled to be striped with pavement markings:
- E Drive N (Beadle Lake Rd to 9 Mile Rd) – 1st Application
- D Drive N (9 Mile Rd to M-311) – 1st Application
- L Drive N (Gravel to 12 Mile Rd) – 2nd Application
- D Drive N (6.5 Mile Rd to Beadle Lake Rd) – 2nd Application
- G Drive N (Raymond Rd to Wattles Rd) – 2nd Application
- E River Rd (Raymond Rd to G Drive N) – 2nd Application
- 8.5 Mile Rd (B Drive N to D Drive N) – 2nd Application
- Grenville (Columbia Ave to City Limits) – 2nd Application
PROJECT UPDATE MARCH 28, 2022:
To prepare for pulverizations that will begin on April 4, contractors have begun cutting driveways and deberming (scraping the grass/organic material away from the edge of the road).
Starting on April 4, E Drive N will be pulverized between 6 ½ Mile Rd. and Beadle Lake Road.
After E Drive N is pulverized, Westbrook (off of Raymond Rd) will be pulverized, and then the Presidents Streets (Eisenhower, Nixon, Eastland, Dulles, Humphrey, McArthur, Knowland).