Click here for an interactive map of the Emmett Township Local Road Project
2022 construction overview:
Read the press release
PROJECT UPDATE NOVEMEBER 10, 2022:
The remaining roads in Post Addition will be paved Thursday (11/10) and Friday (11/11), along with Bowers Dr, east of Funston. Also paving in a couple patches on Martin and Enwood.
The seasonal change is upon us and the 2022 Construction Season is coming to a close. Any remaining punch list items may be delayed until spring.
PROJECT UPDATE NOVEMBER 3, 2022:Post Addition: Curb replacement is in progress with paving to follow.
Bowers Ave : In the process of scheduling paving operations.
Slope restoration continues on 6 Mile Rd and E Drive N.
Punch list items are being reviewed and resolved.
Post Addition: Curb replacement is in process. Paving will occur once the curb project is complete, weather permitting.
Bowers Ave : Roadway will be prepped prior to paving, weather permitting.
Creekside: Gravel is scheduled to be added to the dig-out this morning. Asphalt work will be then scheduled.
Slope restoration continues on 6 Mile Rd and E Drive N. Martin St slope restoration is on-going around the basin.
Pavement marking on 6 Mile Rd, E Drive N, 6 1/2 Mile Rd, Division and Harper Village Dr was completed Monday, 10/24.
Punch list items are being reviewed and resolved.
PROJECT UPDATE OCTOBER 20, 2022:The water main project/underground work has been completed in the Post Addition.
Jericho, E Alden and Lyda in the Post Addition have been milled. Paving after curb replacement is complete. Curb work starting today, 10/20.
Manhole adjustment on Harper Village Dr taking place today, 10/20. (2nd and final phase, then striping will be done)
Bowers Ave from Funston to the dead end will be graded early next week with paving to follow.
A new leaching basin was installed at Martin St and Bradford yesterday, 10/19. Asphalt will be applied next week, weather permitting.
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- Vale St
- Bach/Hoover/Embury/Lamson
- 6 Mile Rd
- 6.5 Mile Rd
- Harper Village Dr
- 6 Mile Rd, (Curbed Area)
- Goldenview
- Oakvale
- Division Drive
- Flowerwood/Petal Ln
- Pine Knoll Dr
The water main project/underground work has been completed in the Post Addition.
Jericho and Lyda in the Post Addition will be milled today, 10/13. We anticipate paving with in the next 2 weeks, weather permitting.
Pavement marking will be taking place on 6 Mile Rd, 6 1/2 Mile Rd, E Drive N, and Harper Village Dr today, 10/13/2022.
Manhole adjustments on Harper Village Dr are scheduled for today, 10/13. (2nd and final phase)
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- Vale St
- Bach/Hoover/Embury/Lamson
- 6 Mile Rd
- 6.5 Mile Rd
- Harper Village Dr
- 6 Mile Rd, (Curbed Area)
- Goldenview
- Oakvale
- Division Drive
- Flowerwood/Petal Ln
- Pine Knoll Dr
Bowers Ave, east of Funston will be graded and paved within the next week.
Slope restoration is currently taking place in the Bach/Hoover/Embury/Lamson subdivision.
Shouldering on E Drive N is scheduled within the next week, weather permitting.
Punchlist items will be reviewed and addressed over the next few weeks.
The following roads have been pulverized. The water main replacement project will be over the next several weeks:
- E Alden
- Richmond
- Walnut Ct
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- Vale St
- Bach/Hoover/Embury/Lamson
- 6 Mile Rd
- 6.5 Mile Rd
- Harper Village Dr
- 6 Mile Rd, (Curbed Area)
- Goldenview
- Oakvale
- Division Drive
- Flowerwood/Petal Ln
- E Drive N, 6.5 mile – Beadle Lake Rd
E Drive North is scheduled be paved today, 9/29.
Slope restoration is currently taking place in the President Street subdivision, followed by Bach/Hoover/Embury/Lamson.
Shouldering on 6 Mile Rd and 6 1/2 Mile Rd has been completed.
The following roads have been pulverized and will have water main replaced over the next several weeks:
- E Alden
- Richmond
- Walnut Ct
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- Vale St
- Bach/Hoover/Embury/Lamson
- 6 Mile Rd
- 6.5 Mile Rd
- Harper Village Dr
- 6 Mile Rd, (Curbed Area)
- Goldenview
- Oakvale
- Division Drive
- Flowerwood/Petal Ln
Pine Knoll Drive paving was completed yesterday.
Flowerwood/Petal Lane will be paved today, 9/22.
Slope restoration is taking place currently in the President Street subdivision.
Shouldering will then continue on Bach/Hoover/Embury/Lamson.
Shouldering on 6 Mile Rd and 6 1/2 Mile Rd is scheduled to begin on Friday 9/23.
The following roads have been pulverized and will have water main replaced over the next several weeks:
- E Alden
- Richmond
- Walnut Ct
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- Vale St
- Bach/Hoover/Embury/Lamson
- 6 Mile Rd
- 6.5 Mile Rd
- Harper Village Dr
- 6 Mile Rd, (Curbed Area)
- Goldenview
- Oakvale
- Division Drive
The following streets have been paved with a base layer of HMA:
- E Drive N, Dead End – Juanita
Pine Knoll Drive and Flowerwood/Petal Lane are scheduled to be milled this morning, 9/15.
Slope restoration will continue this week in the President Street subdivision, followed by Bach/Hoover/Embury/Lamson.
The following roads have been pulverized and will have the water main replaced over the next several weeks:
- E Alden
- Richmond
- Walnut Ct
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- Vale St
- Bach/Hoover/Embury/Lamson
- 6 Mile Rd
- 6.5 Mile Rd
- Harper Village Dr
- 6 Mile Rd, (Curbed Area)
- Goldenview
- Oakvale
- Division Drive
The following streets have been paved with a base layer of HMA:
- E Drive N, Dead End – Juanita
PROJECT UPDATE SEPTEMBER 8, 2022:
Night work paving for Harper Village Dr and 6 Mile Rd are complete. Pavement markings will be applied before the end of the 2022 season.
-Goldenview and Oakvale were paved this week.
-Flowerwood/Petal Lane are scheduled to be milled/paved the week of 9/18
The following roads have been pulverized and will have water main replaced over the next several weeks:
- E Alden
- Richmond
- Walnut Ct
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- Vale St
- Bach/Hoover/Embury/Lamson
- 6 Mile Rd
- 5 Mile Rd
- Harper Village Dr
- 6 Mile Rd, (Curbed Area)
- Goldenview
- Oakvale
The following streets have been paved with a base layer of HMA:
- E Drive N, Dead End – Juanita
Night work for Harper Village Dr and 6 Mile Rd starting on Tuesday August 30
The following roads have been pulverized and will have water main replaced over the next several weeks:
- E Alden
- Richmond
- Walnut Ct
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- Vale St
- Bach/Hoover/Embury/Lamson
- 6 Mile Rd
- 6.5 Mile Rd
The following streets have been paved with a base layer of HMA:
- E Drive N, Dead End – Juanita
PROJECT UPDATE AUGUST 18, 2022:
The following roads have been pulverized and will have the water main replaced over the next several weeks:
- E Alden
- Richmond
- Walnut Ct
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- Vale St
- Bach/Hoover/Embury/Lamson
- 6 Mile Rd
- 6.5 Mile Rd
The following streets have been paved with a base layer of HMA:
- E Drive N, Dead End – Juanita
Shoulder gravel and/or topsoil will be added to recently finished roads within the next few weeks.
We anticipate that E Drive N will be near completion towards the end of this month.
Night work is scheduled for Harper Village Dr and 6 Mile Rd at end of August/early September.
PROJECT UPDATE AUGUST 10, 2022:
Walnut Ct, Alden and Richmond are scheduled to be pulverized this Friday, August 12, as part of the water line replacement project. Door hangers were passed out today to notify residents. Jericho and Lyda will be milled after the water line project is complete.
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- Vale St
- Bach/Hoover/Embury/Lamson
- 6 Mile Rd
- 6.5 Mile Rd
The following streets have been paved with a base layer of HMA:
- E Drive N, Dead End – Juanita
Shoulder gravel and/or topsoil will be added to recently finished roads within the next few weeks.
We anticipate that E Drive N will be near completion towards the end of the month.
Night work is scheduled for Harper Village Dr and 6 Mile Rd at end of August/early September.
PROJECT UPDATE AUGUST 4, 2022:
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- Vale St
- Bach/Hoover/Embury/Lamson
- 6 Mile Rd
- 6.5 Mile Rd
The following streets have been paved with a base layer of HMA:
- E Drive N, Dead End – Juanita
We anticipate that E Drive N will be near completion towards the end of the month.
Night work is scheduled for Harper Village Dr and 6 Mile Rd at end of August/early September.
Pulverizing in the Post Addition for the water service line replacement will occur in the next 2 weeks and we anticipate paving by October.
Shoulder gravel and/or topsoil will be added to the recently completed roads within the next few weeks.
The E Drive N culvert project is near completion and we anticipate the road will be open to traffic by the end of the day.
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- Vale St
- Bach/Hoover/Embury/Lamson
- 6 Mile Rd
- 6.5 Mile Rd
The following streets have been paved with a base layer of HMA:
- E Drive N, Dead End – Juanita
Shoulder gravel and/or topsoil will be added to recently finished roads within the next week or two.
PROJECT UPDATE JULY 22, 2022:The E Drive N culvert is in progress
Topsoil and/or shoulder gravel will be added to recently finished roads with in the next couple of weeks.
The following streets have been paved with a top layer of HMA:
- Vale Street
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- Bach / Hoover Subdivision
- 6 Mile Rd
- 6.5 Mile Rd
- President Streets Subdivision
The following streets have been paved with a base layer of HMA:
- E Drive N, Dead End – Juanita
UPDATE: Vale street should be finished with paving today. Planning on finishing the Bach/Hoover Subdivision Wednesday and 6.5 Mile Rd Thursday
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
The following streets have been paved with a base layer of HMA:
- Vale St
- Bach/Hoover Subdivision
- E Drive N, Dead End – Juanita
- 6 Mile Rd
- 6.5 Mile Rd
PROJECT UPDATE JULY 7, 2022:
Work has begun on the E Drive North culvert replacement and the road is closed at this time.
Vale street should be finished with paving on July 11. Planning on finishing the Bach/Hoover Subdivision on July 13 and 6.5 Mile Rd on July 14.
PROJECT UPDATE JUNE 30, 2022:
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- President Streets
- Bach/Hoover Subdivision
- E Drive N, Dead End – Juanita
- 6 Mile Rd
- 6.5 Mile Rd
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- Vale St
PROJECT UPDATE JUNE, 23 2022:
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
The following streets have been paved with a base layer of HMA:
- President Streets
- Bach/Hoover Subdivision
- E Drive N, Dead End – Juanita
- 6 Mile Rd
- 5 Mile Rd
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- Vale St
6 Mile and 6.5 Mile are scheduled to be paved with a base layer today (6 mile), and tomorrow (6.5 Mile).
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
The following streets have been paved with a base layer of HMA:
- President Streets
- Bach/Hoover Subdivision
- E Drive N, Dead End - Juanita
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Vale St
- 6.5 Mile Rd
- 6 Mile Rd
*Roads that are currently pulverized will be watered regularly for dust control
PROJECT UPDATE JUNE 9, 2022:
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
- Christian Dr
- President Streets
- Bach/Hoover Subdivision
- E Drive N (6.5 Mile to Dead End)
- Vale St
- 6.5 Mile road
- 6 Mile Rd
PROJECT UPDATE JUNE 2, 2022:
Paving is currently scheduled for Christian Drive this morning around 10:00 a.m.
The following streets have been paved with a base layer of HMA:
- Lamson
- Bach
- Embury
- Hoover
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
The following streets are currently pulverized/milled:
- E Drive N (6.5 Mile to Dead End)
- Vale St
- 6.5 Mile road
- 6 Mile Rd
- Christian Dr
*Roads that are currently pulverized will be watered regularly for dust control
PROJECT UPDATE MAY 26, 2022:
The following streets have been paved with a base layer of HMA:
- Lamson. The rest of the neighborhood, (Bach, Embury, Hoover) is not paved yet, we didn’t pave Tuesday due to scheduling conflict. Tried Wednesday but were rained out. Should be back there next week
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Vale St
- 6.5 Mile road
- 6 Mile Rd
- Christian Dr
*Roads that are currently pulverized will be watered regularly for dust control
PROJECT UPDATE MAY 23, 2022:The President Streets Subdivision, (Eisenhower, Nixon, Eastland, Dulles, Humphrey and Knowland) have had the base layer of HMA paved.
The following streets are scheduled to be paved with a base layer of HMA on Tuesday, 5/24/22:
- Hoover, Bach, Embury, Lamson
- E Drive N, Beadle Lake Rd – Dead End
The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Vale St
- 6.5 Mile road
- 6 Mile Rd
*Roads that are currently pulverized will be watered regularly for dust control
PROJECT UPDATE MAY 13, 2022:The following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
- Powell
- Hammond, N of Westbrook
- Westbrook
- Ryan’s Run
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Eisenhower (Milled)
- President Streets Subdivision
- Vale St
- 6.5 Mile road
*Roads that are currently pulverized will be watered regularly for dust control
PROJECT UPDATE MAY 5, 2022:The following streets have been paved with a base layer of HMA:
- Powell
- Hammond, N of Westbrook
- Westbrook
The Following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, both sides
- Tower Rd
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Eisenhower (Milled)
- President Streets Subdivision
- Vale St
- 6.5 Mile road
Trenching has begun on 6 mile rd with pulverization to follow, likely next week.
Christian and Ryan’s Run will be milled today ,5/5, after being rescheduled from this past Tuesday.
PROJECT UPDATE APRIL 28, 2022:The following streets have been paved with a base layer of HMA:
- Juanita, from E Drive N to End
- Tower Rd
- Westbrook
- Powell
- Hammond, N of Westbrook
The Following streets have been paved with a top layer of HMA:
- Orbit
- Juanita, from 6.5 Mile – End
The following streets are currently pulverized/milled and will have driveways removed (if needed) while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Eisenhower (Milled)
- President Streets Subdivision
- Vale St
- 6.5 Mile road
The following streets are scheduled to be pulverized/milled Tuesday, 5/3/22:
- Christian Drive/Ryan’s Run (Mill 1.5”)
Punch List Items rolled over from last year will be addressed in the coming weeks based on priority.
PROJECT UPDATE APRIL 21, 2022:The following streets have been paved with a base layer of HMA:
- Juanita
- Orbit
- Westbrook
- Powell
- Hammond, N of Westbrook
The following streets have been pulverized and will have driveways removed while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Tower Rd
- Eisenhower (Milled)
- President Streets Subdivision
- Vale St
The following streets are scheduled to be pulverized this Thurs/Fri:
- Bach/Hoover/Embury
- 6.5 Mile Rd
The following streets were striped with pavement markings on Wednesday:
- E Drive N (Beadle Lake Rd to 9 Mile Rd) – 1st Application
- D Drive N (9 Mile Rd to M-311) – 1st Application
- L Drive N (Gravel to 12 Mile Rd) – 2nd Application
- D Drive N (6.5 Mile Rd to Beadle Lake Rd) – 2nd Application
- G Drive N (Raymond Rd to Wattles Rd) – 2nd Application
- E River Rd (Raymond Rd to G Drive N) – 2nd Application
- 8.5 Mile Rd (B Drive N to D Drive N) – 2nd Application
- Grenville (Columbia Ave to City Limits) – 2nd Application
Punch List Items rolled over from last year will be addressed in the coming weeks based on priority.
PROJECT UPDATE APRIL 14, 2022:The following streets have been pulverized and will have driveways removed while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Orbit
- Juanita
- Westbrook
- Tower Rd
- Eisenhower (Milled)
The following streets are scheduled to be pulverized this Thurs/Fri:
- President Streets Subdivision
- Vale St
The following streets are next in line for driveway cutting and berm grading:
- Hoover
- Bach
- Embury
The following streets are scheduled to be striped with pavement markings next week:
- E Drive N (Beadle Lake Rd to 9 Mile Rd) – 1st Application
- D Drive N (9 Mile Rd to M-311) – 1st Application
- L Drive N (Gravel to 12 Mile Rd) – 2nd Application
- D Drive N (6.5 Mile Rd to Beadle Lake Rd) – 2nd Application
- G Drive N (Raymond Rd to Wattles Rd) – 2nd Application
- E River Rd (Raymond Rd to G Drive N) – 2nd Application
- 8.5 Mile Rd (B Drive N to D Drive N) – 2nd Application
- Grenville (Columbia Ave to City Limits) – 2nd Application
Punch List Items rolled over from last year will be addressed in the coming weeks based on priority.
PROJECT UPDATE APRIL 7, 2022:The following streets have been pulverized and will have driveways removed while grading and compacting continues:
- E Drive N (6.5 Mile to Dead End)
- Orbit
- Juanita
- Westbrook
The following streets are scheduled to be pulverized next Thurs/Fri:
- President Streets Subdivision
- Tower Rd
- Vale St
The following streets are next in line for driveway cutting and berm grading:
- Hoover
- Bach
- Embury
The following streets are scheduled to be striped with pavement markings on April 14th:
- E Drive N (Beadle Lake Rd to 9 Mile Rd) – 1st Application
- D Drive N (9 Mile Rd to M-311) – 1st Application
- L Drive N (Gravel to 12 Mile Rd) – 2nd Application
- D Drive N (6.5 Mile Rd to Beadle Lake Rd) – 2nd Application
- G Drive N (Raymond Rd to Wattles Rd) – 2nd Application
- E River Rd (Raymond Rd to G Drive N) – 2nd Application
- 8.5 Mile Rd (B Drive N to D Drive N) – 2nd Application
- Grenville (Columbia Ave to City Limits) – 2nd Application
Punch List Items rolled over from last year will be addressed in the coming weeks based on priority.
PROJECT UPDATE APRIL 5, 2022:The following streets have had driveways cut and berm graded and are currently being pulverized this week, April 5 (Mon-Wed):
- E Drive N (6.5 Mile to Dead End)
- Orbit
- Juanita
- Westbrook
- President Streets Subdivision
The following streets are next in line for driveway cutting and berm grading:
- Hoover
- Bach
- Embury
On April 14, the following streets are scheduled to be striped with pavement markings:
- E Drive N (Beadle Lake Rd to 9 Mile Rd) – 1st Application
- D Drive N (9 Mile Rd to M-311) – 1st Application
- L Drive N (Gravel to 12 Mile Rd) – 2nd Application
- D Drive N (6.5 Mile Rd to Beadle Lake Rd) – 2nd Application
- G Drive N (Raymond Rd to Wattles Rd) – 2nd Application
- E River Rd (Raymond Rd to G Drive N) – 2nd Application
- 8.5 Mile Rd (B Drive N to D Drive N) – 2nd Application
- Grenville (Columbia Ave to City Limits) – 2nd Application
PROJECT UPDATE MARCH 28, 2022:
To prepare for pulverizations that will begin on April 4, contractors have begun cutting driveways and deberming (scraping the grass/organic material away from the edge of the road).
Starting on April 4, E Drive N will be pulverized between 6 ½ Mile Rd. and Beadle Lake Road.
After E Drive N is pulverized, Westbrook (off of Raymond Rd) will be pulverized, and then the Presidents Streets (Eisenhower, Nixon, Eastland, Dulles, Humphrey, McArthur, Knowland).